Adobe house renovation – Support wall continue #5




The retaining wall is slowly made. Since last year I was sick a lot and early this year, so it was halfway.

Fate brought me that I had plenty of spare time now, so I continued concreting.

So at least the remaining cement is used.


The formwork is made using a smooth surface door and some block bricks.



The door was drilled in several places. Everywhere 2-2 holes were made, so fence with wire was tied to keep it safe.

At the bottom of the already reinforced iron grid, the logs on the terrace are used as fixed points.


Here is a block-brick section.



The level rises



I'm leaving it for the moment. I would not overload the formwork and myself either :).

Because of the rain I had to cover it.



The next day I pushed the shutter to get out of the concrete.



There is still a shortage here ...



The shutter was further expanded and filled with concrete.



The foil protects the "shutter holes" against concrete cure.



A little further away ... It was a shroud of everything, even from the hungarocell tables :).



The next day the shutter is disassembled.



The hungarocell and planks form a steep edge for continuation.



Formwork moved to continue.



From inside.



That's it, even if it's not perfectly straight everywhere.



The small board was bolted separately to the door leaf because that was all that was missing.



A little vinegar trunk supports, because it will be poured out all the time and there will be heavy pressure on the concrete...



And finally the picture was assembled on the wall next to the stairs .. I solved it without shuttering :).





Even the back was back ...

But finally it was finished (finally).